GUI server hardware requirements
Never deployed these before, well slight lie did deploy a GUI server back in the 3.x days but it didn't do anything useful. I am now looking to deploy a pair of GUI servers for the ReST API support so we can run Kubernetes workloads. The CPU and RAM requirements seem to be quite low. I have a some old spare servers that can be pressed into service for now that more than meet the these requirements with 8 cores and 144GB of RAM. However it just vaguely says "local PV for DB". At the moment the two servers have a RAID6 array of 300GB 10k disks giving ~1TB of usable. Is that sufficient space and will it be performant enough? Should I look to swap them for a RAID 1 of SSD's and what sort of capacity is needed for this local DB? JAB. -- Jonathan A. Buzzard Tel: +44141-5483420 HPC System Administrator, ARCHIE-WeSt. University of Strathclyde, John Anderson Building, Glasgow. G4 0NG
Would be plenty for the gui role as it stands today, The ESS EMS server does not use SSD at all, and it runs the GUI for an ESS cluster. However it’s worth noting that there are changes coming to the GUI / rest API as part of the 5.2.0 / 5.2.1 code in 1H 2024 You might want to reach out to your local IBM resource and ask them to put you in touch with one of the developers for the new experience to explain what’s coming in more detail. Regards, Andrew Beattie Technical Sales Specialist - Storage for Big Data & AI IBM Australia and New Zealand P. +61 421 337 927 E. abeattie@au1.ibm.com Twitter: AndrewJBeattie LinkedIn: ________________________________ From: gpfsug-discuss <gpfsug-discuss-bounces@gpfsug.org> on behalf of Jonathan Buzzard <jonathan.buzzard@strath.ac.uk> Sent: Monday, January 8, 2024 7:18:56 PM To: gpfsug main discussion list <gpfsug-discuss@gpfsug.org> Subject: [EXTERNAL] [gpfsug-discuss] GUI server hardware requirements Never deployed these before, well slight lie did deploy a GUI server back in the 3.x days but it didn't do anything useful. I am now looking to deploy a pair of GUI servers for the ReST API support so we can run Kubernetes workloads. The CPU and RAM requirements seem to be quite low. I have a some old spare servers that can be pressed into service for now that more than meet the these requirements with 8 cores and 144GB of RAM. However it just vaguely says "local PV for DB". At the moment the two servers have a RAID6 array of 300GB 10k disks giving ~1TB of usable. Is that sufficient space and will it be performant enough? Should I look to swap them for a RAID 1 of SSD's and what sort of capacity is needed for this local DB? JAB. -- Jonathan A. Buzzard Tel: +44141-5483420 HPC System Administrator, ARCHIE-WeSt. University of Strathclyde, John Anderson Building, Glasgow. G4 0NG _______________________________________________ gpfsug-discuss mailing list gpfsug-discuss at gpfsug.org http://gpfsug.org/mailman/listinfo/gpfsug-discuss_gpfsug.org
On 08/01/2024 09:37, ANDREW BEATTIE wrote:
Would be plenty for the gui role as it stands today, The ESS EMS server does not use SSD at all, and it runs the GUI for an ESS cluster.
I care not about the GUI role, only the RestAPI support. I am old school and take the view that if you need a GUI to manage your storage then step away from the keyboard :-)
However it’s worth noting that there are changes coming to the GUI / rest API as part of the 5.2.0 / 5.2.1 code in 1H 2024
You might want to reach out to your local IBM resource and ask them to put you in touch with one of the developers for the new experience to explain what’s coming in more detail.
Here is a question can you replace the GUI/RestAPI servers live without service interruption? Say just spin up a couple more and then retire the old ones. Or replace them one at a time? As it stands the machines are pretty old anyway and are spare because firstly the CPU is not supported in ESXi 7+, and then SAS adaptor is not supported in RHEL8+. Hence they are spare. However they work just fine under Ubuntu LTS 22.04 and we are likely to move away from RHEL after RedHat's stunt last year. However I would want to be able to replace them without downtime if required and as funds allow. JAB. -- Jonathan A. Buzzard Tel: +44141-5483420 HPC System Administrator, ARCHIE-WeSt. University of Strathclyde, John Anderson Building, Glasgow. G4 0NG
Here is a question can you replace the GUI/RestAPI servers live without service interruption? Say just spin up a couple more and then retire the old ones. Or replace them one at a time?
I do not see why not, I have certainly had a system where the GUI was originally running on a storage node, then later a dedicated server was bought and spun up, and the GUI role moved over to it without an outage Daniel Daniel Kidger HPC Storage Solutions Architect, EMEA daniel.kidger@hpe.com +44 (0)7818 522266 hpe.com -----Original Message----- From: gpfsug-discuss <gpfsug-discuss-bounces@gpfsug.org> On Behalf Of Jonathan Buzzard Sent: Monday, January 8, 2024 5:32 PM To: gpfsug-discuss@gpfsug.org Subject: Re: [gpfsug-discuss] GUI server hardware requirements On 08/01/2024 09:37, ANDREW BEATTIE wrote:
Would be plenty for the gui role as it stands today, The ESS EMS server does not use SSD at all, and it runs the GUI for an ESS cluster.
I care not about the GUI role, only the RestAPI support. I am old school and take the view that if you need a GUI to manage your storage then step away from the keyboard :-)
However it’s worth noting that there are changes coming to the GUI / rest API as part of the 5.2.0 / 5.2.1 code in 1H 2024
You might want to reach out to your local IBM resource and ask them to put you in touch with one of the developers for the new experience to explain what’s coming in more detail.
Here is a question can you replace the GUI/RestAPI servers live without service interruption? Say just spin up a couple more and then retire the old ones. Or replace them one at a time? As it stands the machines are pretty old anyway and are spare because firstly the CPU is not supported in ESXi 7+, and then SAS adaptor is not supported in RHEL8+. Hence they are spare. However they work just fine under Ubuntu LTS 22.04 and we are likely to move away from RHEL after RedHat's stunt last year. However I would want to be able to replace them without downtime if required and as funds allow. JAB. -- Jonathan A. Buzzard Tel: +44141-5483420 HPC System Administrator, ARCHIE-WeSt. University of Strathclyde, John Anderson Building, Glasgow. G4 0NG _______________________________________________ gpfsug-discuss mailing list gpfsug-discuss at gpfsug.org http://gpfsug.org/mailman/listinfo/gpfsug-discuss_gpfsug.org
participants (3)
-
ANDREW BEATTIE -
Jonathan Buzzard -
Kidger, Daniel