Hi Simon
I was part of a beta program for GPFS (ok, better start saying Spectrum Scale!) 4.1.1, so I've had some experience with the toolkit that installs the protocol nodes. The new protocol nodes MUST be RH7, so it's going to be a bit more of an involved process to migrate to this level than in the past. The GPFS server nodes/client nodes can remain at RH6 is needed.
Overall it works pretty well. You do have the option of doing things manually as well. The guide that describes it is pretty good. If you want to discuss the process in detail, I'd be happy to do so - a bit too much to cover over a mailing list.
Bob Oesterlin