To address this question or problem, please be more specific about:

1) commands and policy rules used to perform or control the migrations and pre-migrations.

2) how the commands are scheduled, how often, and/or by events and mmXXcallbacks.

3) how many files are "okay" and how many are ill-placed.  

4) how many blocks or KB of storage are ill-placed.  (One could determine this by looking at pool free/used blocks stats, then running
restripe to correct all ill-placements and then looking at pool free/used stats again.)

5) As commands and migrations are executed, what is happening that you do not understand or that you believe is incorrect?

Marc K of GPFS (aka "Mister Mmapplypolicy")



From:        "Uwe Falke" <UWEFALKE@de.ibm.com>
To:        "gpfsug main discussion list" <gpfsug-discuss@spectrumscale.org>
Date:        04/24/2018 06:43 AM
Subject:        [gpfsug-discuss] ILM: migrating between internal pools while        premigrated to external
Sent by:        gpfsug-discuss-bounces@spectrumscale.org




Hello, World,
I'd asked this on dW last week but got no reactions:

I am unsure on the viability of this approach:
In a given file system, there are two internal storage pools and one
external (GHI/HPSS).
Certain files are created in one internal pool and are to be migrated to
the other internal pool about one day after file closure.
In addition, all files are to be (pre-)migrated to the external pool
within one hour after closure.
Hence: typically, blocks of a file being already pre-migrated to external
(but not purged on the initial internal pool) are to be moved from one
internal pool to the other.
A slight indication that there might be some issue with such an approach
I've found in a dW post some years back:
https://www.ibm.com/developerworks/community/forums/html/topic?id=77777777-0000-0000-0000-000014797943&ps=25

However, time has passed and this might work now or might not. Is there
some knowledge about that in the community?
If it would not be a reasonable way, we would do the internal migration
before the external one, but that imposes a timely dependance we'd not
have otherwise.



Mit freundlichen Grüßen / Kind regards


Dr. Uwe Falke

IT Specialist
High Performance Computing Services / Integrated Technology Services /
Data Center Services
-------------------------------------------------------------------------------------------------------------------------------------------
IBM Deutschland
Rathausstr. 7
09111 Chemnitz
Phone: +49 371 6978 2165
Mobile: +49 175 575 2877
E-Mail: uwefalke@de.ibm.com
-------------------------------------------------------------------------------------------------------------------------------------------
IBM Deutschland Business & Technology Services GmbH / Geschäftsführung:
Thomas Wolter, Sven Schooß
Sitz der Gesellschaft: Ehningen / Registergericht: Amtsgericht Stuttgart,
HRB 17122


_______________________________________________
gpfsug-discuss mailing list
gpfsug-discuss at spectrumscale.org
https://urldefense.proofpoint.com/v2/url?u=http-3A__gpfsug.org_mailman_listinfo_gpfsug-2Ddiscuss&d=DwIFAw&c=jf_iaSHvJObTbx-siA1ZOg&r=cvpnBBH0j41aQy0RPiG2xRL_M8mTc1izuQD3_PmtjZ8&m=j-JJhNxx8XhgizXxQDuJolplgYxVRVTS6zalCPshD-0&s=oHJJ8ZT4qE3GTSPKyNRVdybeeCQHTeyoDiLg5CvC5JM&e=